Kontain technical perspective · tailings management

Why smaller mines should reconsider geobag tailings storage

A fair smaller-mine comparison: size the filtration plant, allocate its capital over supported production, and price extra civil and lining works from the storage design.

Free cost comparison tool

A fair tailings comparison includes the installed filtration plant, sized for the actual throughput and material. Its capital allocation depends on the dry tonnes processed over the supported operating life. Kontain uses A$1–2/dmt as a working capital sensitivity here, not a verified industry range or a fixed installed price.

Geobags avoid a central filtration plant and allow bag purchases to follow production. Pumps, dosing equipment and engineered pads still need funding. Price the extra civil and lining works from matched storage designs, measured quantities and scoped rates.

Kontain supplies geobags. This is our commercial and technical perspective for mines producing 100,000 to one million dry metric tonnes (dmt) of tailings a year.

Start with capital in the comparison

All figures below are illustrative Australian dollars excluding GST. Selected operating costs are A$10/dmt for each route. The filtration-capital sensitivity is A$1–2/dmt. A complete project estimate must also reconcile storage works, other equipment, reagents, closure and any genuinely different operating tasks.

Cost componentGeobag storageMechanically filtered stack
Upfront process equipmentPumps, dosing and pipework priced for the project; no filter pressInstalled plant priced for throughput, tailings and required availability
Selected operating costsA$10.00/dmtA$10.00/dmt
Initial filtration-plant capital allocationNo filter-plant chargeA$1.00–2.00/dmt working sensitivity
Additional civil and lining worksUp to 20% of the matched civil and lining budget in this planning case; allocate to the capacity those works provideMatched baseline works assessed separately
Selected subtotal before unresolved differencesA$10.00/dmt plus the verified works premium and other bag capitalA$11.00–12.00/dmt plus remaining project costs
Separate standby facilitiesCost from a scoped design; no unsupported lump sum includedCost required standby equipment and capacity on the same basis

The comparison does not establish a fixed percentage saving. Capital can improve the geobag case, but the result depends on plant sizing, supported production, placement cost and the actual storage design. No assumed downtime saving is included. Costs outside the selected scope are not treated as free or equal without checking them.

Size the plant, then allocate its capital

Use installed capital divided by the dry tonnes the plant is expected to process: capital allocation = installed plant cost ÷ lifetime processed dmt. Include required thickening, services, electrical works, structures, installation and commissioning in the quoted scope. Match the design to peak duty, feed variability, moisture target and availability, not annual tonnage alone. Published case studies show that tailings characteristics and the available filtration technology can materially change the equipment and capital required. [15]

The following arithmetic illustrates A$1–2/dmt for different installed capital and operating-life assumptions. The capital amounts are assumptions, not quotations. A published lifecycle study uses twenty years as an assessment period; that is a modelling choice, not a universal plant lifespan. [11] A mine's supported production schedule sets the denominator; an equipment design life does not justify processing tonnes the mine has not demonstrated.

Installed plant assumptionAnnual dry tonnesSupported operating periodLifetime processed dry tonnesInitial capital allocation
A$5 million500,000 dmt/year10 years5 million dmtA$1.00/dmt
A$10 million500,000 dmt/year10 years5 million dmtA$2.00/dmt
A$10 million500,000 dmt/year20 years10 million dmtA$1.00/dmt

At 500,000 dmt/year and 350 operating days, average production is approximately 1,430 dmt per operating day, before allowance for within-day downtime and peak duty. A quoted plant for a materially different scale should not be carried into this example unchanged. Conversely, A$1–2/dmt is not a cap: a shorter project, difficult filtration duty or more expensive installation can exceed it.

Cash timing still matters. The plant must be funded before operation, while bags can be bought progressively. An all-in contract rate may already recover plant capital; do not add it twice. These simple allocations exclude financing, residual value and subsequent renewals. Include major replacements once, either in maintenance or sustaining capital. The calculator's capital scenarios explicitly apply a 500,000 dmt/year, A$10 million plant over ten or twenty years; users can replace the capital and production inputs.

Maintenance and production continuity belong in the cost review

Pressure filtration brings a substantial maintenance task. The BHP/Rio Tinto Tailings Management Consortium guide attributes approximately 80% of pressure-filter maintenance activities to cloths and plates. It also describes a ten-hour shutdown every two weeks for more substantial maintenance, and says this time must be allowed for in equipment sizing, utilisation and redundancy. That is a planning example, not a universal shutdown schedule for every plant. [12]

A cost estimate can understate the burden if it uses optimistic cloth life, incomplete maintenance labour or insufficient standby capacity. Review cloths, plates, valves, hydraulics, feed pumps, spares and major renewals against the actual duty. The guide also warns that designing around favourable or composite tailings samples can leave a filtration plant undersized when the feed changes. These are reasons to test the operating envelope and maintenance allowance, rather than rely on the filtration rate alone. [12]

If usable filtration capacity falls below tailings production and the buffer or permitted alternative route fills, the processing plant may have to slow or stop. The commercial consequence can extend well beyond the repair bill. Assess the residual production constraint after standby equipment, storage and recovery capacity are accounted for; lost contribution margin, restart costs and delayed cash flow need their own assessment. Filter downtime is not automatically mine downtime, and deferred production is not automatically permanently lost production.

Geobags offer a practical way to keep a local filling problem from becoming a production bottleneck. In a suitable layout, an affected bag or branch can be isolated and flow directed to prepared spare bags or the separately engineered standby deposition area. This needs installed connections, available capacity, adequate drainage and filtrate management, spare pumping/dosing capacity where required, and a tested changeover procedure. Buying a spare bag alone does not provide an operating contingency.

There is a documented mining example: SRK's May 2022 Segovia technical report describes geotubes being used at the El Chocho facility during filter-press downtime. This supports geobags as a practical contingency option for suitable material; it does not establish a universal cost or availability advantage. [13]

The advantage is simpler, distributed contingency and fewer mechanical dewatering components. Shared pumps, power, dosing, pipelines, access and drainage can still interrupt a bag operation, so these common dependencies must be covered. Well-designed and maintained filtration plants can also achieve high availability; published work describes availability above 90% with appropriate equipment, layout and maintenance. [14]

The comparison tables take no assumed production-loss penalty against filtration and give bags no assumed uptime saving. Routine maintenance is already included in the A$4/dmt filtration input. Add only costs omitted from that scope, then compare the remaining interruption exposure for both options. Any demonstrated continuity benefit would be additional to the capital comparison above.

Include the work after filtration

A useful comparison follows the same incoming tailings stream through to its final stored condition. A filtration-only operating rate stops too early. The filter produces cake; the project must still get that cake into an appropriately formed and managed stack.

Published research recognises this distinction. Carneiro and Fourie's Western Australian conceptual study included transport, spreading, moisture conditioning and compaction. It used a placement rate of A$3.65/t for a hypothetical 2 Mtpa operation with a 1 km haul. Annual maintenance, labour and administration were excluded on an assumed-similar basis. The lesson is to examine what a quoted rate includes, rather than assume every published total covers the same work. [1]

SRK describes fully compacted dewatered stacks as continuing earthmoving operations whose operating costs can exceed those of the dewatering plant. Its discussion also shows how structural and non-structural zones can change the required compaction effort. The placement allowance should follow the proposed deposition design. [2]

Geobags installed in their permanent position combine dewatering and deposition. Solids accumulate inside the unit while water drains out; separate transport and compaction of filter cake are avoided. That benefit belongs in the comparison alongside the bag purchase. Temporary dewatering followed by excavation or relocation is a different arrangement and should include its subsequent handling costs. [3, 7]

A competitive operating comparison

The following Australian-dollar example excludes GST. The bag inputs are Kontain's budgeting allowances for suitable heavy tailings. Bag purchase prices increase with unit size, so the A$7/dmt supply allowance stays constant across the selected payload range. Filtration at A$4/dmt and placement at A$6/dmt are editable comparison inputs.

Selected operating costGeobag storageMechanically filtered stack
Bag supply per dry tonne storedA$7.00/dmt—
Bag deployment and connectionsA$2.50/dmt—
Pumping and dosing electricityA$0.30/dmtIncluded in filtration
Routine equipment servicing, minor parts and maintenance labourA$0.20/dmtIncluded in filtration
Filtration including process power, operators and routine maintenance—A$4.00/dmt
Loading, transport, conditioning, spreading and compaction as required—A$6.00/dmt
Selected operating subtotalA$10.00/dmtA$10.00/dmt

The A$0.50/dmt combined geobag electricity and maintenance provision is a manual budgeting allowance, rather than a published industry benchmark. Pumping duty, pipeline length, slurry abrasion and operating hours determine the site allowance. At 500,000 dmt/year it represents A$250,000 annually.

These are selected operating subtotals. The opening table identifies initial filtration capital and the additional bag-site construction premium separately. Bag filling and dosing supervision, excavator use and other water-management support must be included wherever they are additional. Remaining capital, storage infrastructure, polymer and closure are assessed separately. Filtration power, operators and routine maintenance are already inside the filtration allowance and must not be counted again. Placement contractor or hire rates may also recover equipment capital; check their scope before adding loaders, trucks or conveyors as separate capital.

On operating costs alone, the mechanical placement break-even is A$6.00/dmt: A$10.00 for bags less A$4.00 for filtration. Any additional bag-site cost raises that threshold, while filtration-plant capital lowers it. For example, a verified A$0.40/dmt works premium and A$1–2/dmt filtration capital would give A$4.40–5.40/dmt, before other differences. The tool shows both the operating comparison and the comparison including entered site and capital allowances.

The historical A$3.65/t placement assumption, if treated as a 2018 dry-tonne rate, becomes approximately A$4.83–5.00/dmt when indexed to September 2026 using the ABS Other Heavy and Civil Engineering Construction series. This is useful cost context rather than a contractor quotation: the original rate's precise price base and dry-tonne interpretation are assumptions in that escalation. [1, 4]

A relevant throughput reference is WSP's 2026 Peruvian study. Its first stage processes 1,500 dmt/day for 360 days, approximately 540,000 dmt/year. Filtration operating cost is US$2.51/t, including electricity, operating personnel and maintenance. Loading and an 8.6 km truck haul add US$4.75/t, giving a reported subtotal of US$7.26/t. Initial filtration-plant capital is separately estimated at US$20.79 million. [5]

These are Peruvian estimates in US dollars, with a substantial haul distance. They demonstrate why a filtration operating rate alone cannot represent the complete system cost. The loading-and-haul increment should not be assumed to include every subsequent conditioning and compaction activity. This is a specific overseas engineering estimate, not a representative installed price for every smaller mine. The A$1–2/dmt capital sensitivity above is a separate Kontain planning assumption, not a conversion or conclusion from WSP's estimate.

Labour should follow the work

Geobag deployment and connections are periodic tasks. A shared site crew can install the next units, connect lines and return to other work between activities. Filling management and inspections remain part of the operating plan. Mechanical systems likewise require operators and maintenance support, plus the people and equipment involved in their placement route.

The calculator allows either measured deployment hours or a manual A$2.50/dmt allowance. For context, four people at A$100 per person-hour working eight hours on a 1,000-dmt bag cost A$3.20/dmt before equipment. The A$2.50 allowance corresponds to 6.25 crew-clock hours at that rate and payload. Actual bag size, deployment time and shared duties determine the appropriate input.

At 2,000 dmt per bag, 100,000 dmt/year requires about 50 units annually, or approximately one per week. At 600,000 dmt/year, it requires about 300 units annually, or six per week. This is a manageable planning basis for scheduling deployment, filling and drainage within an engineered pad layout. Bag supply remains A$7/dmt in the example as the unit price scales with capacity.

Cost the extra civil and lining works from the layout

Kontain's planning case allows up to 20% extra for civil and lining works to account for gentler bag-stack slopes. Apply that percentage only to the comparable earthworks and lining scope. It is not 20% of the whole project, not a guaranteed 20% increase in plan area, and not an automatic A$0.50/dmt charge. The actual design may need a smaller premium; 20% is the upper allowance in this scenario, not a universal limit for every site.

For the 35,000 m² example, the following transparent cost basis produces approximately A$200,000 extra:

Civil and lining exampleAmount or basis
Matched baseline footprint used for this illustration35,000 m²
Assumed baseline civil and lining budgetA$1,000,000
Implied combined cost across that footprintApproximately A$28.60/m²
Additional civil and lining allowance20% × A$1,000,000 = A$200,000
Total civil and lining budget including the premiumA$1,200,000

This is a budgeting example, not a contractor rate. The combined area rate is inferred from the A$1 million budget; actual earthworks should be priced from measured volumes and lining from its required area and system. Here 35,000 m² is explicitly the matched baseline footprint, not a verified final geobag design. Confirm the area basis, ground conditions and quantities for the project.

Convert the A$200,000 premium using the usable dry-tonne capacity of the works it buys. If that footprint provides 500,000 dmt of storage, the premium is A$0.40/dmt; if it provides one million dmt, it is A$0.20/dmt. Those capacities are arithmetic illustrations, not estimates derived from 35,000 m². Plan area alone cannot establish capacity. Stacking height, geometry, dry density, access and stability must establish it.

Do not spread one pad's A$200,000 across the entire mine life if additional pads will be built. For example, ten equivalent 500,000-dmt pads would provide five million dmt and incur A$2 million of additional works, still A$0.40/dmt before unused capacity and timing effects. If one footprint really does accommodate the full lifetime production, its one-off premium can instead be divided by those lifetime tonnes.

At the illustrative A$0.40/dmt premium, selected geobag costs would be A$10.40/dmt versus A$11–12/dmt for mechanical filtration and placement including the capital sensitivity. This is approximately 5.5–13.3% lower on that selected scope, before other equipment, standby and unmatched project costs. It is not a promised whole-project saving.

A separate standby deposition area remains a useful option to assess. One month at 500,000 dmt/year means approximately 41,667 dmt of capacity, but that target does not establish a construction price. Use spare capacity in the approved layout where suitable, or price a separate pad, drainage and access from the design. Standby construction remains unpriced in this selected comparison. An unpriced standby provision is an outstanding cost, not a free facility.

Standby deposition is separate from emergency spill containment and stormwater storage. Bund dimensions follow credible releases, rainfall, foundations and whole-stack stability. Shared upstream costs remain in both routes; identify and cost any real difference once.

Wet storage has a substantial construction cost

A TSF raise benefits from an existing facility; a new storage development may need foundations, roads, drainage and water infrastructure from the outset. Divide each cost by the usable dry capacity that expenditure creates. Annual mine production and storage volume in cubic metres are different denominators.

For a published Australian example, Aeris reported A$17.3 million for a Cracow TSF upgrade adding approximately one million cubic metres and around three years of production capacity. That is A$17.30/m³. At an assumed dry density of 1.4 dmt/m³, the equivalent is A$12.36/dmt of added capacity; a project-specific dry density is required for the conversion. This was an expansion, not a new facility. [6]

Kontain's discussions with mine operators also include stage allowances around A$10–15/dmt and markedly higher new-facility costs. Two confidential Australian examples were reported at approximately A$45 million for two million dmt and A$30 million for one million dmt: A$22.50/dmt and A$30/dmt respectively. These are operator-reported cost-and-capacity pairs, retained anonymously as project context rather than published market benchmarks.

Construction cost is only one part of wet storage. Deposition, water return, monitoring, maintenance and closure also belong in the whole-life estimate. At the same time, published studies contain lower-cost wet-storage options. The commercial case for bags is strongest when it is established from the site's actual alternatives, rather than a universal dam rate.

Operational benefits beyond the rate per tonne

Geobags offer a simpler process at the storage location. Pumping and filling pressure initiate drainage, followed by continued water release and consolidation under gravity, self-weight and subsequent loading. Each bag performs its dewatering function without a continuously operating mechanical press. This reduces the mechanical equipment associated with the dewatering step, while pumping and dosing duties remain straightforward items to cost. [3, 7]

Enclosing the tailings suppresses dust from the stored fines and avoids dust-generating cake transfer and placement activities where the bags remain in position. The fabric provides continuing surface containment as the material dries. Normal road, spill and later excavation controls still apply, but the exposed tailings surface is fundamentally different from an open stack. [8]

Bag geometry and surface containment also reduce direct rainfall exposure and can limit rewetting compared with loose, exposed material. Rain sheds from the curved surface, while the contained solids retain their position. The fabric is permeable, so this advantage works with a graded pad and effective drainage; it is not a waterproof barrier. Australian geotextile-tube experience reports reduced direct rewetting, supporting this practical benefit. [9]

An exposed filtered stack must accommodate rainfall, changing moisture and trafficability through its deposition and stormwater design. Depending on the material and climate, this can involve conditioning, working-area management and compaction. Some designs use uncompacted zones, so the allowance should follow the design rather than a blanket rule. [10]

For future reuse, identifiable bag cells can keep dewatered material accessible and segregated. That can support recovery planning without relying on an active wet impoundment. Opening bags, removing fabric and any subsequent processing are then costed as part of the recovery operation.

Manage risk through controlled filling and smaller inventories

Geobags change the form and distribution of the stored material. Dewatering reduces mobile water, while separate units divide the incoming slurry inventory into smaller compartments. This is an important distinction from retaining a large connected inventory of water and wet tailings. It gives designers a more localised initial loss-of-containment scenario to manage.

During filling, the operating procedure sets maximum fill height and pressure, controlled flow and clear stop criteria. The system design can specify overflow, pressure-relief or automatic shutdown arrangements to provide further protection. These are practical safeguards against overfilling, supported by inspection of connections, fabric and seams. Overfilling is an operating condition to control, not an inherent reason to reject the method. [3]

As drainage and consolidation progress, the material becomes less mobile and behaves increasingly as a contained soil mass rather than pumped slurry. A fabric defect in a consolidated unit is therefore a different event from a failure during filling. The design still considers erosion, local release and interaction between units; neither the likelihood nor the consequences of every possible event can be reduced to a single bag without considering the stack as a whole. [7]

Foundation performance, overall stability, drainage and closure remain normal engineering responsibilities. The advantage is a storage arrangement with reduced mobile-water inventory and defined operating units, rather than a claim of zero risk. That provides a sound basis for comparing consequence, inspection and maintenance requirements alongside cost.

Work through the comparison with Kontain

For suitable tailings at smaller mines, geobags can combine competitive cost with simpler dewatering, less handling, dust suppression and progressive expenditure. The worked comparison includes electricity and maintenance, an explicit plant-capital sensitivity and a civil-and-lining premium tied to storage capacity. Standby and other unresolved costs must be priced before drawing a whole-project conclusion. Regulators, designers and operators should give this option meaningful consideration alongside wet storage and mechanically filtered stacks. Their value becomes clear when the comparison includes the work required to deliver the final stored material, rather than stopping at the outlet of a filter.

Kontain's Tailings Cost Comparison tool is free to use through our website. We strongly recommend a presentation and a guided comparison with Kontain before relying on the results for a project decision. The calculation is straightforward; choosing consistent payload, labour, plant, placement and storage inputs requires knowledge of the proposed operation.

We can work with the mine's technical and operating teams to establish those inputs, compare the complete alternatives and identify the site information needed for a useful estimate. The tool remains freely available for users who already understand their inputs and want to explore their own scenarios.

Use the free calculator on the Kontain website: https://kontainsolutions.com/tailings-cost-comparison/

Explore the geobag design tools for layout and capacity planning: https://kontainsolutions.com/design-tools/geobag-design-tools

Arrange a presentation and guided project comparison with Kontain: https://kontainsolutions.com/request-quote

Sources and calculation basis

[1] Carneiro A and Fourie AB 2018. A conceptual cost comparison of alternative tailings disposal strategies in Western Australia. Paste 2018, pp. 442, 446–447 and 451. https://papers.acg.uwa.edu.au/d/1805_36_Carneiro/36_Carneiro.pdf

[2] Norambuena Mardones RE, Caldwell-Crystal C and Cobos D 2023. How high is too high? Challenges on the next generation of dewatered tailings stacks. Paste 2023, pp. 468–469. https://papers.acg.uwa.edu.au/d/2355_35_Norambuena/35_Norambuena.pdf

[3] Assinder PJ, Breytenbach M, Wiemers J and Hörtkorn F. Utilizing geotextile tubes to extend the life of a Tailings Storage Facility. HUESKER and SRK, sections 4.2 and 5. https://www.huesker.com.au/fileadmin/media/Scientific_Revised_Paper/P761_Utilizing_geotextile_tubes_to_extend_the_life_of_a_Tailings_Storage_Facility_.pdf

[4] Australian Bureau of Statistics. Producer Price Indexes Australia September 2026, Table 17, series A85220823L. The escalation assumes a 2018 price base and dry-tonne interpretation. https://www.abs.gov.au/statistics/economy/price-indexes-and-inflation/producer-price-indexes-australia/sep-2026/6427017.xlsx

[5] Gonzales G and Huillca G 2026. Detailed engineering for the implementation of filtered tailings in Peruvian underground mining. WSP, Paste 2026, pp. 9–10. Costs retained in US dollars. https://papers.acg.uwa.edu.au/d/2655_13_Gonzales/13_Gonzales.pdf

[6] Aeris Resources 2024. Annual Report, pp. 2 and 10. https://aerisresources.com.au/wp-content/uploads/2024/10/Aeris_AR_2024_WEB.pdf

[7] da Silva F 2023. Stacked deposits of thickened and filtered fluid fine tailings using geotextile tubes concepts and lessons learned updates. Paste 2023, pp. 640–645 and 649. https://papers.acg.uwa.edu.au/d/2355_49_da_Silva/49_da_Silva.pdf

[8] Solmax. GEOTUBE Dewatering for Mining and Mineral Processing, APAC brochure, p. 5. https://geofabrics.co/sites/default/files/2024-07/GEOTUBE_Dewatering_for_mining_and_mineral_processing_APAC_1123_Web(1).pdf

[9] Smith M 2009. Geotextile tubes in environmental applications. Australian Geomechanics Society Sydney Chapter Symposium, pp. 110 and 119. https://geomechanics.org.au/wp-content/uploads/2023/04/K-Smith-paper.pdf

[10] BHP and Rio Tinto Tailings Management Consortium 2026. Unlocking Large Tonnage Filtered Tailings Stacks A Geotechnical Perspective, March, pp. 12 and 24. https://www.bhp.com/-/media/project/bhp1ip/bhp-com-en/documents/sustainability/tailings-storage-facilities/260508_whitepaperfilteredstacks.pdf

[11] Chinchankar AP 2024. Lifecycle cost comparison: modern solid-bowl centrifuge technology outperforms filtration in tailings dewatering. Paste 2024, pp. 27–38. Supplier-authored comparison using a 20-year assessment period; cited for that modelling basis only. https://papers.acg.uwa.edu.au/p/2455_01_Chinchankar/

[12] BHP and Rio Tinto Tailings Management Consortium 2026. Filtered Stacked Tailings: A Guide for Study Managers, edition 1.2, March, sections 6.6.1–6.6.3, pp. 112–117. https://www.bhp.com/-/media/project/bhp1ip/bhp-com-en/documents/sustainability/tailings-storage-facilities/260508_filteredstacktailingshandbook.pdf

[13] SRK Consulting (U.S.), Inc. 2022. NI 43-101 Technical Report, Prefeasibility Study, Segovia Project, Antioquia, Colombia. Effective 31 December 2021; issued May 2022, section 18.2.2, p. 334. Filed by Aris Mining in September 2023. Historical operating example. https://www.aris-mining.com/investors/financials/sec-filings/content/0001193125-23-229367/d460434dex9928.htm

[14] Wisdom T 2019. Maintaining high availability and low operational costs for filtered tailings facilities. Paste 2019, pp. 337–348. Cited for achievable availability with suitable design and maintenance. https://papers.acg.uwa.edu.au/p/1910_23_Wisdom/

[15] Hahn J 2024. How tailing characteristics affect capex and opex in filtration: two case studies. Paste 2024, pp. 105–114. Supplier-authored technical comparison; cited for material and technology dependence, not small-mine price benchmarks. https://papers.acg.uwa.edu.au/p/2455_07_Hahn/